Nieuws
Field notes from Industrie 4.0 in de praktijk: what we tested, what failed, and what we would repeat on the next line.
Factories rarely need more technology in one step. They need a sequence of small changes that can be checked on the floor before the next change follows. These notes record that sequence as it happened.
Each entry describes a single observation or trial. Where a result is still open, we say so.

A planning session in which the team agreed on one measurable bottleneck for the pilot.
Progress so far
Phase 1
Baseline measurement
We logged cycle times and stops for two weeks before changing anything.
Phase 2
Sensor placement
Sensors were moved twice until the signal was stable during normal shifts.
Phase 3
Data review
Operators and engineers reviewed the logs together and removed duplicate alarms.

Transport routes between buildings were the first thing we measured, not the robots.
What we changed
- Stops are now recorded with a reason code chosen by the operator
- Sensor data is time-stamped at the controller, not at the server
- Pilot targets are written down before a trial starts

The planning room, where the weekly review of logs takes place.

A dashboard view of stop causes, kept open during the last trial week.